Overview
The rate of growth of generation capacities in public sector is in line with the additions to the
installed capacity. During the last 50 years the thermal generation registered a spectacular growth.
However, the growth in hydro generation was very poor. Also on the nuclear front, 10 Nuclear power
plants accounted for only around 2% of total utility generation.Owing to the decline in hydro development
and prevailing peak power deficits, coal-fired thermal power units are often used for meeting peak loads.
Poor performance of India's existing generating units has been a principal cause of worry. The average plant
load factor (PLF) of thermal power stations in India is less than 60%, but varies considerably across the
regions. In contrast, hydro power stations have far better track record due to the fact that their performance
relies largely on water flow.The sector wise and region wise generating capacities are given in the table 1 below:
Generation Sector
Table 1
Sector and Region wise Generating Capacities
|
|
Sector |
Total |
Hydro |
Thermal |
Wind |
Nuclear |
| |
|
|
|
Coal |
Gas |
Diesel |
Total |
|
|
| NR |
State |
17897 |
6400 |
10574 |
901 |
14 |
11490 |
6.4 |
0.00 |
| |
Private |
558 |
386 |
0 |
0 |
0 |
0 |
172.1 |
0.00 |
| |
Central |
13642 |
3810 |
6340 |
2312 |
0 |
8652 |
| 1180 |
| |
Sub Total |
30979 |
10596 |
16914 |
3213 |
14 |
20142 |
178 |
1180 |
| WR |
State |
19611 |
4180 |
14041 |
1346 |
17 |
15404 |
26 |
0.0 |
| |
Private |
5740 |
447 |
2290 |
2398 |
0.2 |
4688 |
606 |
0.0 |
| |
Central |
7387 |
875 |
4460 |
1292 |
0.0 |
5752 |
0.0 |
760 |
| |
Sub Total |
32739 |
5502 |
20791 |
5036 |
17.2 |
25844 |
632 |
760 |
| SR |
State |
18743 |
10394 |
7392 |
562 |
362 |
8317 |
31 |
0.0 |
| |
Private |
4508 |
43 |
510 |
1738 |
576 |
2824 |
1640 |
0.0 |
| |
Central |
7120 |
0.0 |
5990 |
350 |
0.0 |
6340 |
0.0 |
780 |
| |
Sub Total |
30371 |
10437 |
13892 |
2650 |
938 |
17482 |
1671 |
780 |
| ER |
State |
7914 |
2255 |
5538 |
100 |
17 |
5655 |
3.7 |
0.0 |
| |
Private |
1443 |
0.0 |
1441 |
0.0 |
0.0 |
1441 |
1.5 |
0.0 |
| |
Central |
8551 |
204 |
8257 |
90 |
0.0 |
8347 |
0.0 |
0.0 |
| |
Sub Total |
17909 |
2459 |
15237 |
190 |
17 |
15444 |
5.2 |
0.0 |
| NER |
State |
1097 |
274 |
330 |
351 |
142 |
823 |
0.3 |
0.0 |
| |
Private |
24 |
0.0 |
0.0 |
24 |
0.0 |
24 |
0.0 |
0.0 |
| |
Central |
1235 |
860 |
0.0 |
375 |
0.0 |
375 |
0.0 |
0.0 |
| |
Sub Total |
2357 |
1134 |
330 |
750 |
142 |
1223 |
0.3 |
0.0 |
| Island |
State |
49 |
5 |
0.0 |
0.0 |
44.02 |
44 |
0.0 |
0.0 |
| |
Private |
20 |
0.0 |
0.0 |
0.0 |
20 |
20 |
0.0 |
0.0 |
| |
Central |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| |
Sub Total |
69 |
5 |
0.0 |
0.0 |
64 |
64 |
0.0 |
0.0 |
| India |
State |
65314 |
23510 |
37877 |
3260 |
598 |
41736 |
68 |
0.0 |
| |
Private |
12294 |
876 |
4241 |
4160 |
597 |
8998 |
2419 |
0.0 |
| |
Central |
37935 |
5749 |
25047 |
4419 |
0.0 |
29466 |
0.0 |
2720 |
| |
Sub Total |
115544 |
30135 |
67165 |
11839 |
1195 |
80201 |
2488 |
2720 |
During the 9th Five Year Plan (1997-2002), the Indian Government had fixed the target of 40245.2MW for
capacity addition, comprising 29545.5MW of thermal, 9819.7MW of hydro and 880MW of nuclear. Unfortunately,
due to various constraints, the Government itself could add only about 19,000MW as compared to the planned
addition. A capacity addition of 41110 MW has been targeted for the 10th five-year plan; details are given in Table 2 below.
Table 2 - Capacity Addition Programme for 10th Five Year Plan
| |
Hydro |
Thermal |
Nuclear |
Cumulative Capacity |
| Central Sector |
8742 |
12790 |
1300 |
22832 |
| State Sector |
4481 |
6676 |
0 |
11157 |
| Private Sector |
1170 |
5941 |
0 |
7121 |
| Overall |
14393 |
25407 |
1300 |
41110 |
Source: Annual Repport 2002-03 , Ministry Of power
Capacity Addition Achieved during First Three Years of 10th Plan
Year |
Capacity Addition (MW) |
Centre |
State |
Total |
2002-03 |
1210.0 |
1440.30 |
2650.30 |
2003-04 |
3035.0 |
916.62 |
3951.62 |
2004-05
(up to Feb'05) |
2585.0 |
1058.92 |
3643.92 |
Source Annual Report-Ministry of Power, Govt. of India Ministry of Power is accelerating the generation
growth through various policy measures. In the remaining period of two years of 10th Plan and five years
of 11th Plan, government is planning for Capacity addition of around 70,000MW.
The overall achievements in the power sector in last fifty years and the power requirement forecast
for 10th and 11th Plan are given in Table 3 & 4.
Table 3 - Growth of Installed Generating Capacity
By Year Ending |
Installed Generating Capacity (MW) |
Centre |
Nuclear |
Thermal |
March-1950 |
559 |
- |
1,152 |
March-1960 |
1,530 |
- |
2,343 |
March-1970 |
6,134 |
420 |
7,592 |
March-1975 |
7,529 |
640 |
10,153 |
March-1980 |
11,384 |
640 |
16,857 |
March-1990 |
18,308 |
1,565 |
43,764 |
March-1995 |
20,833 |
2,005 |
58,113 |
March-1998 |
21,891 |
2,225 |
64,150.78 |
March-2000 |
23,627 |
1,840 |
69,474.76 |
March-2001 |
25,141.78 |
2,860 |
73,628.30 |
March-2002 |
26,261 |
2,720 |
75,936.30 |
March-2003 |
26,910 |
2,720 |
78,342.57 |
March-2004 |
29,500 |
2,720 |
79,838.19 |
March-2001 |
30,335 |
2,860 |
83,266 |
Source: Annual Report, 2004-05 Ministry of Power
Table 4 - All India Power requirement Forecast for 10th, 11th Plan
Year |
Energy Requirement
MKWh |
Peak load
MW |
2006-07 |
7,81,863 |
1,30,944 |
2011-12 |
10,58,440 |
1,76,647 |
Source: 15th Electric Power Survey of India
Funding
Power Sector, hitherto, had been funded mainly through budgetary support and external borrowings.
But given the budgetary support limitations, due to growing demand from other sectors, particularly
social sector and the severe borrowing constraints, the Government is expecting a larger role in the
power sector from private enterprises. Necessary legal provisions have been in place and policy changes
are being implemented to encourage participation from private sector. Private sector is permitted to set
up coal, gas or liquid based thermal projects, hydel projects and wind or solar projects of any size.
Foreign equity participation up to 100% in the power sector under the automatic route is also permitted.
Foreign Investors can enter into a joint venture with an Indian partner for financial and/or technical
collaboration and also for setting up of renewable energy based power generation projects. The liberalized
foreign investment approval regime is aimed at facilitating foreign investment and transfer of technology
through joint ventures.