member's login


home about us.... industry update.... placement cell
Industry Update : Generation Sector
Overview
The rate of growth of generation capacities in public sector is in line with the additions to the installed capacity. During the last 50 years the thermal generation registered a spectacular growth. However, the growth in hydro generation was very poor. Also on the nuclear front, 10 Nuclear power plants accounted for only around 2% of total utility generation.Owing to the decline in hydro development and prevailing peak power deficits, coal-fired thermal power units are often used for meeting peak loads. Poor performance of India's existing generating units has been a principal cause of worry. The average plant load factor (PLF) of thermal power stations in India is less than 60%, but varies considerably across the regions. In contrast, hydro power stations have far better track record due to the fact that their performance relies largely on water flow.The sector wise and region wise generating capacities are given in the table 1 below:

Generation Sector

Table 1

Sector and Region wise Generating Capacities


Sector
Total
Hydro
Thermal
Wind
Nuclear
       
Coal
Gas
Diesel
Total
   
NR State 17897 6400 10574 901 14 11490 6.4 0.00
  Private 558 386 0 0 0 0 172.1 0.00
  Central 13642 3810 6340 2312 0 8652 1180
  Sub Total 30979 10596 16914 3213 14 20142 178 1180
WR State 19611 4180 14041 1346 17 15404 26 0.0
  Private 5740 447 2290 2398 0.2 4688 606 0.0
  Central 7387 875 4460 1292 0.0 5752 0.0 760
  Sub Total 32739 5502 20791 5036 17.2 25844 632 760
SR State 18743 10394 7392 562 362 8317 31 0.0
  Private 4508 43 510 1738 576 2824 1640 0.0
  Central 7120 0.0 5990 350 0.0 6340 0.0 780
  Sub Total 30371 10437 13892 2650 938 17482 1671 780
ER State 7914 2255 5538 100 17 5655 3.7 0.0
  Private 1443 0.0 1441 0.0 0.0 1441 1.5 0.0
  Central 8551 204 8257 90 0.0 8347 0.0 0.0
  Sub Total 17909 2459 15237 190 17 15444 5.2 0.0
NER State 1097 274 330 351 142 823 0.3 0.0
  Private 24 0.0 0.0 24 0.0 24 0.0 0.0
  Central 1235 860 0.0 375 0.0 375 0.0 0.0
  Sub Total 2357 1134 330 750 142 1223 0.3 0.0
Island State 49 5 0.0 0.0 44.02 44 0.0 0.0
  Private 20 0.0 0.0 0.0 20 20 0.0 0.0
  Central 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
  Sub Total 69 5 0.0 0.0 64 64 0.0 0.0
India State 65314 23510 37877 3260 598 41736 68 0.0
  Private 12294 876 4241 4160 597 8998 2419 0.0
  Central 37935 5749 25047 4419 0.0 29466 0.0 2720
  Sub Total 115544 30135 67165 11839 1195 80201 2488 2720

During the 9th Five Year Plan (1997-2002), the Indian Government had fixed the target of 40245.2MW for capacity addition, comprising 29545.5MW of thermal, 9819.7MW of hydro and 880MW of nuclear. Unfortunately, due to various constraints, the Government itself could add only about 19,000MW as compared to the planned addition. A capacity addition of 41110 MW has been targeted for the 10th five-year plan; details are given in Table 2 below.

Table 2 - Capacity Addition Programme for 10th Five Year Plan

  Hydro Thermal Nuclear Cumulative Capacity
Central Sector 8742 12790 1300 22832
State Sector 4481 6676 0 11157
Private Sector 1170 5941 0 7121
Overall 14393 25407 1300 41110


Source: Annual Repport 2002-03 , Ministry Of power

Capacity Addition Achieved during First Three Years of 10th Plan

Year
Capacity Addition (MW)
Centre
State
Total
2002-03
1210.0
1440.30
2650.30
2003-04
3035.0
916.62
3951.62
2004-05
(up to Feb'05)
2585.0
1058.92
3643.92

Source Annual Report-Ministry of Power, Govt. of India Ministry of Power is accelerating the generation growth through various policy measures. In the remaining period of two years of 10th Plan and five years of 11th Plan, government is planning for Capacity addition of around 70,000MW.

The overall achievements in the power sector in last fifty years and the power requirement forecast for 10th and 11th Plan are given in Table 3 & 4.

Table 3 - Growth of Installed Generating Capacity

By Year Ending
Installed Generating Capacity (MW)
Centre
Nuclear
Thermal
March-1950
559
-
1,152
March-1960
1,530
-
2,343
March-1970
6,134
420
7,592
March-1975
7,529
640
10,153
March-1980
11,384
640
16,857
March-1990
18,308
1,565
43,764
March-1995
20,833
2,005
58,113
March-1998
21,891
2,225
64,150.78
March-2000
23,627
1,840
69,474.76
March-2001
25,141.78
2,860
73,628.30
March-2002
26,261
2,720
75,936.30
March-2003
26,910
2,720
78,342.57
March-2004
29,500
2,720
79,838.19
March-2001
30,335
2,860
83,266

Source: Annual Report, 2004-05 Ministry of Power

Table 4 - All India Power requirement Forecast for 10th, 11th Plan

Year
Energy Requirement
MKWh
Peak load
MW
2006-07
7,81,863
1,30,944
2011-12
10,58,440
1,76,647

Source: 15th Electric Power Survey of India

Funding
Power Sector, hitherto, had been funded mainly through budgetary support and external borrowings. But given the budgetary support limitations, due to growing demand from other sectors, particularly social sector and the severe borrowing constraints, the Government is expecting a larger role in the power sector from private enterprises. Necessary legal provisions have been in place and policy changes are being implemented to encourage participation from private sector. Private sector is permitted to set up coal, gas or liquid based thermal projects, hydel projects and wind or solar projects of any size. Foreign equity participation up to 100% in the power sector under the automatic route is also permitted.

Foreign Investors can enter into a joint venture with an Indian partner for financial and/or technical collaboration and also for setting up of renewable energy based power generation projects. The liberalized foreign investment approval regime is aimed at facilitating foreign investment and transfer of technology through joint ventures.